Project Description
The Cascade Crossing Transmission Project (Cascade Crossing), proposed by Portland General Electric (PGE), is subject to review and environmental analysis by state and federal agencies and the Confederated Tribes of Warm Springs (CTWS). The state review process will be conducted by the Oregon Department of Energy – Energy Facility Siting Council (ODOE-EFSC), and the federal review will be led by the U.S. Forest Service (USFS).
PGE proposes to:
- Build, operate and maintain approximately 22 miles of single and 187 miles of double circuit, 500 kilovolt (kV) transmission line. The new line would cross 64 percent privately-owned lands, 20 percent lands managed by federal agencies, 14 percent lands on the Warm Springs Reservation of Oregon and 2 percent state or municipal lands.
- Build three new substations and upgrade two existing substations.
PGE’s purpose for this project is to help meet Oregon’s growing energy needs, enable development of more renewable energy projects and enhance reliability of the region’s electrical grid.
In addition, PGE may need to upgrade its existing transmission system in the Willamette Valley, including upgrading its 230 kV line from Salem to Oregon City, and installing new conductors on existing subtransmission lines in Salem to reliably distribute the additional electricity brought to the valley by the Cascade Crossing transmission line.
Cascade Crossing is a multi-year project with three main components:
- Planning and design - PGE will continue to refine the planning and design of Cascade Crossing throughout the process. PGE has developed preliminary routing options, submitted project permitting applications to the state and federal agencies and the CTWS, and will continue to meet with communities, landowners and other project stakeholders. PGE’s proposed and alternate corridors parallel existing transmission corridors wherever possible.
- Permitting - ODOE-EFSC will administer the state review of PGE’s proposed project, while USFS will lead the federal agencies' review process. The CTWS will manage the permitting process across the reservation.
- Construction - If the agencies approve the project, PGE anticipates beginning construction in 2013 with project completion in 2015.